产地深圳是否进口否品牌SANTAK/山特型号3C3PRO-20KS货号3C3类型通信电源输入电压380V输出功率380V调制方式脉冲宽度调制(PWM)式标称容量90%产品认证iso9001电源类型UPS不间断电源额定容量60KVA/54KW工作频率50/60Hz自适应工作湿度5%~95%,无凝露工作温度0 ~ 40?C规格1台控制方式自动化控制频率范围42 - 72Hz输出电压380Vac/220Vac+/-1%输出频率50/60Hz输入电压范围380Vac/220Vac +/-1%输入频率Upto94%;ECO模式下大于98%外型尺寸(W*H*D)600 x 720x1200mm晶体管连接方式单端式加工定制否工作效率94%双转换模式效率负载调整率1电压调整率-50%~20%负载类型用电设备负载稳压率-50%~20%输出电压精度+/-1%电源名称UPS不间断电源订货号3C3小包装数一台物料编号是否跨境出口货源否系列山特城堡系列3C3通讯方式NMC智能卡,Modbus卡,RS232接口卡扩展功能通讯接口和通讯选件保护方式浪涌保护工作环境温度0~40°C重量177
山特UPS不间断电源3C3PRO20KS 1.2度电。存储的电能等于容量乘以电池电压,实际充电时一部分变成了热能,消耗的电网电能要多点比如如果一个电瓶100AH,电压12V,那么能存储100*12=1.2KWH的电能,也就是1.2度。
100Ah*12v=1200vah=1.2度,也就是说充满此电瓶需要1.2度电,因为1va=1w,1200vah=1200wh,要是50w12v的电机,就是1200wh/50w=24h=24小时。
比如:一个1.2V500mah的电池表示它以1.2v的电压,500ma的电流放电,能够放电一小时。那么所耗的电量=UIt=1.2V*0.5A*1h=0.6瓦时,就是0.6度。
Sante UPS uninterruptible powersupply 3C3PRO20KS (hereinafter referred to as Party A) in acomputer room, it is found that the battery pack (100Ah/20HR) ofthe ups (20KVA) power supply in the computer room has reached itsservice life, and some internal resistance is large, which has morethan 8 hao, according to the requirements of the safe operation ofParty A's computer room, the battery pack 30 only needs to bereplaced.
Apply for
1. After the inspection reportis submitted to Party A, the replacement plan and budget shall bedetermined after communication with relevant personnel and leadersof Party A's technical department. Confirm the replacement of100Ah/10HR batteries, and Party A begins to prepare the purchase ofbatteries for this project.
2. After the battery purchaseis completed, the construction date of the project is determinedthrough negotiation with Party A.
3. Party A's technicaldepartment shall submit the application report for this operationto its superior leader according to the procedure. Due to the earlycommunication and the fact that the machine room is a relativelyimportant operating machine room for Party A, the application wasapproved on the same day.
山特UPS不间断电源3C3PRO20KS 更换一组Ups蓄电池,好像非常简单,其实对于一个运营机房来说没有那么容易,因为牵涉到机房的安全运行问题,它是一个比较重要且复杂的工程,从沟通确定方案到领取材料组织施工,有很多工作要做,每个环节都仔细考虑过的,特别是施工环节不能有差错。下面就以近施工的一个工程为案例讲述更换UPS电源蓄电池全部过程。